Work Between November 18 and December 2, 2022
Mayor Bowser is committed to eliminating all roadways, alleys, and sidewalks in poor condition in Washington, DC by 2024 through the PaveDC initiative. This Weekly Construction Update lists all of the road, alley, and sidewalk paving projects that will be under construction during the next two weeks.
The 2021 Paving Plan is published on the PaveDC website with the start of the construction season occurring. The website also includes separate tabs for sidewalks scheduled for repair, and the Alley Restoration Plan for Fiscal Year 2021. For more information about these projects, please visit DDOT’s interactive tool, PaveDC.
For frequently asked questions about the 2021 paving plan, please visit https://ddot.dc.gov
Please note: Work may be adjusted depending on weather and other conditions. Additional projects may be added to this list. DDOT contacts residents and businesses within the work zones before work begins. Unless otherwise noted, work is not conducted on weekends.
Table of Contents
Citywide Pavement Restoration Projects
Citywide Sidewalk Restoration Projects
Citywide Alley Restoration Projects
Contact Information
Citywide Pavement Restoration Projects
image
DDOT is committed, improving, and restoring local roadways through pavement restoration. Residents should expect paving activities at the following locations over the next two weeks, weather permitting:
Ward 1
11th Street NW Between Kenyon Street NW and Lamont Street NW
17th Street NW Between Euclid Street NW and Fuller Street NW
17th Street NW Between Fuller Street NW and Columbia Road NW
17th Street NW Between Irving Street NW and Kenyon Street NW
17th Street NW Between Kenyon Street NW and Kilbourne Place NW
5th Street NW Between 4th Street NW and Gresham Place NW
5th Street NW Between Gresham Place NW and Harvard Street NW, Michigan Avenue NW
California Street NW Between 18th Street NW and 19th Street NW
Columbia Road NW Between 20th Street NW and California Street NW
Columbia Road NW Between Mintwood Place NW and Belmont Road NW
Columbia Road NW Between Sherman Avenue NW and 11th Street NW
Columbia Road NW Between Wyoming Avenue NW and 20th Street NW
Irving Street NW Between 16th Street NW and Mount Pleasant Street NW
Irving Street NW Between Georgia Avenue NW and Sherman Avenue NW
Irving Street NW Between Warder Street NW and Georgia Avenue NW
Kilbourne Place NW Between 17th Street NW and 18th Street NW
Ontario Road NW Between 18th Street NW and Ontario Place NW
Ward 2
23rd Street NW Between Wyoming Avenue (N) NW and Kalorama Road NW
9th Street NW Between N Street NW and O Street NW
Florida Avenue NW Between Q Street (W) NW and 23rd Street NW
N Street NW Between 9th Street NW and 10th Street NW
Street NW Between 13th Street NW and Vermont Avenue NW
P Street NW Between 14th Street NW and 15th Street NW
P Street NW Between 15th Street NW and 16th Street NW
P Street NW Between 16th Street NW and 17th Street NW
Q Street NW Between 20th Street NW and 21st Street NW
Ward 3
28th Street NW Between McGill Ter NW and Calvert Street NW
Ward 4
3rd Street NE Between Oneida Street NE and Peabody Street NE
3rd Street NE Between Peabody Street NE and Quackenbos Street NE
3rd Street NE Between Quackenbos Street NE and Quintana Place NE
3rd Street NE Between Quintana Place NE and Rittenhouse Street NE
Emerson Street NW Between 4th Street NW and 5th Street NW
Emerson Street NW Between New Hampshire Avenue NW and 3rd Street NW
Ward 5
24th Street NE Between Perry Street NE and Quincy Street NE
24th Street NE Between Quincy Street NE and Randolph Street NE
Perry Street NE Between 24th Street NE and 25th Place NE
Ward 6
5th Street SE Between G Street SE and Virginia Avenue SE
6th Street SE Between G Street SE and I Street SE
6th Street SE Between I Street SE and Virginia Avenue SE
M Street SE Between 12th Street SE and Water Street SE
Ward 7
37th Place SE Between 37th Street SE and Dead-End SE
42nd Street NE Between Dix Street NE and Eads Street NE
42nd Street NE Between Eads Street NE and Edson Place NE
42nd Street NE Between Edson Place NE and Foote Street NE
54th Street SE Between Bass Place SE and C Street SE
54th Street SE Between C Street SE and Call Place SE
Bay Lane SE Between Ridge Road SE and Burns Place SE
Burns Court SE Between Burns Place SE and Burns Place SE
Burns Place SE Between Bay Lane SE and C Street SE
Burns Place SE Between Burns Court SE and Bay Lane SE
Cape Dr SE Between C Street SE and C Street SE
Chaplin Street SE Between Hilltop Terrace SE and Burns Street SE, H Street SE
Cloud Place NE Between 51st Street NE and Division Avenue NE
Cloud Place NE Between Division Avenue NE and 53rd Street NE
Dix Street NE Between 57th Street NE and 58th Street NE
Drake Street SE Between 53rd Street SE and 54th Street SE
G Street SE Between Hilltop Terrace SE to Chaplin Street SE
Citywide Sidewalk Restoration Projects
sidewalk
As part of DDOT’s commitment to the improvement and restoration of local sidewalks, construction activities will occur at the following locations throughout the next two weeks.
Ward 4
14th Street NW Between Alaska Avenue NW and Floral Street NW
Kalmia Road NW Between 13th Street NW and Morningside Drive NW
Kalmia Road NW Between 14th Street NW and 16th Street NW
Kalmia Road NW Between Eastern Avenue NW and Georgia Avenue NW
Citywide Alley Restoration Projects
Alleypalooza
DDOT is improving alleys across the city. Once work begins, access to parts of the alley under construction will be closed, and parking is restricted. In emergency situations, access may be permitted by notifying DDOT. Work is estimated to take about two weeks, weather permitting.
Ward 4
Square No 3343: Alley bound by Tuckerman Street, NW, 2nd Street NW, Sheridan Street NW, and 3rd Street NW
Square No 3401: Alley bound by Farragut Place, NW, North Capitol Street NW, First Street NW, and Gallatin Street N.W
Square No 3710: Alley bound by Nicholson Street, NE, 2nd Street NE, New Hampshire Avenue NE, and 3rd Street NE
Citywide Guardrails and Impact Attenuators Upgrade and Repair
1
DDOT preventive maintenance and repair of guardrails and impact attenuators occur at the following locations throughout the next two weeks.
Ward 3
Mass Avenue SB at North and South of Macomb Street NW
Ward 6
14th Street NB at Ramp to EB Maine Avenue SW
SW Freeway WB at Exit Ramp to U S Capitol, SW
Ward 7
Anacostia Freeway SB at Ramp and EB Pennsylvania Avenue SE Left
Anacostia Freeway SB at Ramp and EB Pennsylvania Avenue SE Right
Citywide Highway Structures Repair Projects
1
As part of DDOT’s commitment to the improvement and restoration of Highway Structures, preventive maintenance for bridges and other highway related structures will occur at the following locations throughout the next two weeks.
Ward 3
Chain Bridge Over Potomac River
Theodore Roosevelt Bridge Over Potomac River
Ward 4
14th Street Bridge (Southbound) Over Potomac River and Ohio Drive
Ward 5
Rhode Island Avenue Over North Capitol Street
Ward 6
Southwest Freeway Over South Capitol Street
Ward 7
Ramp and Beginning Road Over Kenilworth Avenue Southbound
Contact Information
For more information about the latest DDOT happenings, follow us on Twitter and Instagram; like us on Facebook; or visit the website at www.ddot.dc.gov or DDOT’s blog, d.delivers.
For media inquiries, please call (202) 465-6112. For constituent inquiries, please call (202) 671-2700 or click here to find contact information for DDOT’s community engagement specialists.

This entry was posted in News. Bookmark the permalink.